Capacity
Not disclosed
Waiting
0.9 yrs
Stage
Local/state review
Verification
Verified (primary source)
Estimated investment waiting
Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).
Timeline
- Sep 26, 2025Public Service Company of Colorado's Motion for Extraordinary Protection of Highly Confidential Information — Filing
- Sep 26, 2025Hearing Exhibit 101, Direct Testimony of Jared M. Luner — Filing
- Sep 26, 2025Hearing Exhibit 102, Direct Testimony of Aaron D. Wilson — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-1 (Public Slip Sheet) — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-2 (Public Slip Sheet) — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-3 (Project Vicinity Maps - Goose Creek and May Valley) — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-4 (CPP Engineering Impact Study) — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-5 (CPP Engineering Impact Study - Additional Sensitivity) — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-6 (Electranix Independent Review of CPP Engineering Impact Study) — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-7 (Project Cost Estimates - Goose Creek and May Valley) — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-8 (Public Slip Sheet) — Filing
- Sep 26, 2025Hearing Exhibit 102, Attachment ADW-9 (POWER Engineers Noise & EMF Studies - Goose Creek and May Valley) — Filing
- Sep 26, 2025Attachment A, Counsel NDA — Filing
- Sep 26, 2025Attachment B, SME NDA — Filing
- Sep 26, 2025Attachment C, Affidavit — Filing
- Sep 26, 2025Public Service Company - CPCN — Filing
- Oct 1, 2025Notice of Application Filed — Filing
- Oct 17, 2025UCA's Highly Confidential Nondisclosure Agreements — Filing
- Oct 17, 2025UCA's Nondisclosure Agreements — Filing
- Oct 17, 2025UCA's Highly Confidential Nondisclosure Agreements — Filing
- Oct 29, 2025Notice of Intervention as of Right by Trial Staff of the Commission, Entry of Appearance, Notice Pursuant to Rule 1007(a) and Rule 1401, and Request for Hearing — Filing
- Oct 31, 2025Utility Consumer Advocate’s Notice of Intervention as a Matter of Right, Entry of Appearances and Request for a Hearing — Filing
- Nov 5, 2025The Commission deemed the application complete and referred to an Administrative Law Judge by minute entry. — Filing
- Nov 25, 202525A-0409E Motion to Approve Procedural Schedule — Filing
- Dec 22, 2025Hearing Exhibit 102, Direct Testimony of Aaron D. Wilson — Filing
- Dec 22, 2025Notice of Filing Substitutions to Hearing Exhibits and Attachments of Public Service Company of Colorado and Unopposed Request for a Two Business Day Extension of Time — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-9, Noise & EMF Studies (Goose Creek and May Valley) — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-8, Hitachi Tariff Estimates (Goose Creek and May Valley) — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-7, Project Cost Estimates (Goose Creek and May Valley) — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-6, Electranix Review of Engineering Impact Study — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-5, Engineering Impact Study Additional Sensitivity — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-4, Colorado's Power Pathway Engineering Impact Study — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-3, Project Vicinity Maps (Goose Creek and May Valley) — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-2, General Arrangements (Goose Creek and May Valley) — Filing
- Dec 22, 2025Hearing Exhibit 102, Attachment ADW-1, One-Line Diagrams (Goose Creek and May Valley) — Filing
- Dec 23, 2025Notice of Technical Difficulty Experienced with the Commission's E-Filing System — Filing
- Jan 16, 2026Hearing Exhibit 200, Answer Testimony of Staff Witness Ha Ho — Filing
- Jan 16, 2026Trial Staff's Notice of Filing Answer Testimony and Attachments — Filing
- Jan 16, 2026Hearing Exhibit 200, Attachment HH-1, PSCo Responses to CPUC 5-2 — Filing
- Jan 16, 2026Hearing Exhibit 200, Attachment HH-2, PSCo Responses to CPUC 1-9 — Filing
- Jan 16, 2026Hearing Exhibit 300, Kuykendoll Answer Testimony — Filing
- Jan 16, 2026Hearing Exhibit 300, Attachment KK-2 — Filing
- Jan 16, 2026Hearing Exhibit 300, Attachment KK-1 — Filing
- Feb 13, 2026Hearing Exhibit 104, Rebuttal Testimony of Aaron D. Wilson — Filing
- Feb 13, 2026Hearing Exhibit 103, Rebuttal Testimony of Jared M. Luner — Filing
- Feb 13, 2026Hearing Exhibit 104, Attachment ADW-12 (Public Service Response to Discovery Request CPUC1-9) — Filing
- Feb 13, 2026Hearing Exhibit 104, Attachment ADW-11 (Attachment CPUC1-6.A1 to Public Service's Response to Discovery Request CPUC1-6) — Filing
- Feb 13, 2026Hearing Exhibit 104, Attachment ADW-10 (CPP Engineering Impact Study - Updated Analysis) — Filing
- Feb 13, 2026Hearing Exhibit 103, Attachment JML-1 (Staff's Response to Discovery Request PSCo1-4) — Filing
- Feb 13, 2026Hearing Exhibit 104, Executable Attachment ADW-11 (Attachment CPUC1-6.A1 to Public Service's Response to Discovery Request CPUC1-6) — Filing
- Feb 23, 2026Notice of Filing Corrections to Pre-filed Testimony and Attachments of Public Service Company of Colorado — Filing
- Feb 23, 2026Hearing Exhibit 102, Attachment ADW-4, Colorado's Power Pathway Engineering Impact Study, Rev. 1 — Filing
- Feb 26, 2026Hearing Exhibit 105, Unanimous Comprehensive Settlement Agreement — Filing
- Feb 26, 2026Unopposed Motion to Approve Unanimous Comprehensive Settlement Agreement, Amend Procedural Schedule, and Request for Waiver of Response Time — Filing
- Mar 3, 2026Hearing Exhibit 106, Settlement Testimony of Jared M. Luner — Filing
- Mar 3, 2026Executable PSCo Witness List — Filing
- Mar 3, 2026Public Service Hearing Exhibit List — Filing
- Mar 3, 2026Executable Public Service Exhibit List — Filing
- Mar 3, 2026PSCo Witness List — Filing
- Mar 3, 2026Notice of Filing of Hearing Exhibit List and Witness List of Public Service Company of Colorado — Filing
- Mar 3, 2026Trial Staff's Exhibits and Witnesses Lists — Filing
- Mar 3, 2026UCA's Witness and Exhibit List — Filing
- Mar 3, 2026Notice of Filing Joint Cross-Examination Matrix — Filing
- Mar 3, 2026Joint Cross-Examination Matrix — Filing
- Mar 3, 2026Joint Cross-Examination Matrix (executable) — Filing
- Mar 3, 2026Trial Staff's Notice of Filing Settlement Testimony — Filing
- Mar 3, 2026Hearing Exhibit 201, Settlement Testimony of Staff Witness Ha Ho — Filing
- Mar 17, 2026Settling Parties' Joint Response to Decision No R26-0140-I — Filing
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Colorado Public Utilities Commission's public e-filing search. No structured location field is published; this project will not appear on the map until geocoded another way.