WaitingForPower
generation · Other

Public Service Company (CO PUC Docket 25A-0367E)

CO

Capacity
Not disclosed
Waiting
1.0 yrs
Stage
Local/state review
Verification
Verified (primary source)

Estimated investment waiting

Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).

Timeline

  • Sep 2, 2025
    Public Service Company of Colorado’s Motion for Extraordinary Protection of Highly Confidential InformationFiling
  • Sep 2, 2025
    Hearing Exhibit 101, Direct Testimony and Attachments of Michael V. PascucciFiling
  • Sep 2, 2025
    Hearing Exhibit 102, Direct Testimony and Attachments of Bradley D. MorrisonFiling
  • Sep 2, 2025
    Hearing Exhibit 102, Attachment BDM-2 (Public Slip Sheet)Filing
  • Sep 2, 2025
    Hearing Exhibit 102, Attachment BDM-3 (Public Slip Sheet)Filing
  • Sep 2, 2025
    Hearing Exhibit 102, Attachment BDM-4, Pawnee Solar+Storage Project Construction SchedulesFiling
  • Sep 2, 2025
    Hearing Exhibit 102, Attachment BDM-5, Noise and Magnetic Field Analysis ReportFiling
  • Sep 2, 2025
    Attachment C - Affidavit of Michael V. PascucciFiling
  • Sep 2, 2025
    Attachment B - Attorney HC NDAFiling
  • Sep 2, 2025
    Attachment A - Subject Matter Expert HC NDAFiling
  • Sep 2, 2025
    Hearing Exhibit 102, Attachment BDM-1, Pawnee Solar+Storage Location MapFiling
  • Sep 2, 2025
    Hearing Exhibit 101, Attachment MVP-2 (Public Slip Sheet)Filing
  • Sep 2, 2025
    Hearing Exhibit 101, Attachment MVP-1 (Public Slip Sheet)Filing
  • Sep 2, 2025
    Public Service Company - CPCNFiling
  • Sep 4, 2025
    Notice of Application FiledFiling
  • Sep 24, 2025
    UCA Highly Confidential Nondisclosure AgreementsFiling
  • Sep 24, 2025
    UCA Nondisclosure AgreementsFiling
  • Oct 1, 2025
    The Utility Consumer Advocate’s Notice of Intervention as a Matter of Right, Entry of Appearances, and Request for a HearingFiling
  • Oct 3, 2025
    Climax Molybdenum Company's Motion to Intervene PermissivelyFiling
  • Oct 7, 2025
    Notice of Intervention as of Right by Trial Staff of the Commission, Entry of Appearance, Notice Pursuant to Rule 1007(a) and Rule 1401, and Request for HearingFiling
  • Oct 7, 2025
    Confidential and Highly Confidential NDA--FanyoFiling
  • Oct 8, 2025
    The Commission deemed the application complete and referred to an Administrative Law Judge by minute entry.Filing
  • Oct 17, 2025
    25A-0367E Motion to Approve Procedural ScheduleFiling
  • Nov 18, 2025
    Notice of Filing CorrectionsFiling
  • Nov 18, 2025
    Attachment A, Corrections SummaryFiling
  • Nov 18, 2025
    Hearing Exhibit 102, Attachment BDM-3 (Public Slip Sheet), Rev.1Filing
  • Nov 18, 2025
    Hearing Exhibit 101, Attachment MVP-1 (Public Slip Sheet), Rev.1Filing
  • Jan 16, 2026
    25A-0367E_Joint Motion for Variance_Extension of TimeFiling
  • Jan 27, 2026
    25A_0367E_Second_Joint Motion for Variance_Extension of TimeFiling
  • Feb 4, 2026
    25A_0367E_Notice of Settlement in PrincipleFiling
  • Feb 6, 2026
    Hearing Exhibit 104, Settlement Testimony of Michael V. PascucciFiling
  • Feb 6, 2026
    Hearing Exhibit 103, Settlement AgreementFiling
  • Feb 6, 2026
    25A-0367E_Motion to Approve Settlement AgreementFiling

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: Sourced from the Colorado Public Utilities Commission's public e-filing search. No structured location field is published; this project will not appear on the map until geocoded another way.