Public Service Company (CO PUC Docket 24A-0560E)

CO

Capacity
Not disclosed
Waiting
1.7 yrs
Stage
Local/state review
Verification
Verified (primary source)

Estimated investment waiting

Not estimated: Investment-waiting is only estimated for projects with capacity measured in MW (generation/storage). This project's capacity is measured differently (e.g. MTPA, or pipeline length/diameter).

Timeline

  • Dec 20, 2024
    Attachment D - Wrozek VerificationFiling
  • Dec 20, 2024
    Hearing Exhibit 105, Attachment NGK-3_Barr ERP Portfolio Evaluation Summary Letter 12-5-2024Filing
  • Dec 20, 2024
    Public Service Company of Colorado's Verified Omnibus Motion for Extraordinary Protection of Highly Confidential Information, and for Waiver of Rules 3206(e)(IV)-(VI) and 3206(f)(IV)-(V) Regarding Noise and Magnetic Field LevelsFiling
  • Dec 20, 2024
    Hearing Exhibit 105, Direct Testimony of Noel G. Klinnert (Public)Filing
  • Dec 20, 2024
    Hearing Exhibit 106, Direct Testimony of Jennifer L. ChesterFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Direct Testimony of S Parker WrozekFiling
  • Dec 20, 2024
    Hearing Exhibit 103, Direct Testimony of Andrew SiebenalerFiling
  • Dec 20, 2024
    Hearing Exhibit 101, Direct Testimony of Alice K JacksonFiling
  • Dec 20, 2024
    Hearing Exhibit 102, Direct Testimony of Michael V PascucciFiling
  • Dec 20, 2024
    Attachment C - Pascucci AffidavitFiling
  • Dec 20, 2024
    Attachment B - Subject Matter Expert HC NDAFiling
  • Dec 20, 2024
    Hearing Exhibit 103, Attachment AWS-1_ERP_CEP_ Ph II_Transmission Planning StudyFiling
  • Dec 20, 2024
    Hearing Exhibit 103, Attachment AWS-2_Leetsdale-Elati Transmission StudyFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Attachment SPW-1 Public Slip SheetFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Attachment SPW-2_Denver Metro MapsFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Attachment SPW-3 Public Slip SheetFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Attachment SPW-4_Denver Metro Line DrawingsFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Public Attachment SPW-5_Daniels Park Path Noise and EMFFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Public Attachment SPW-6_Smoky Hill Path Noise and EMFFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Public Attachment SPW-7_Cherokee Area Noise and EMFFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Attachment SPW-8_5283 Leetsdale-Elati MapFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Attachment SPW-9 Public Slip SheetFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Attachment SPW-10 Public Slip SheetFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Attachment SPW-11_Leetsdale-Elati Duct Bank DrawingFiling
  • Dec 20, 2024
    Hearing Exhibit 104, Public Attachment SPW-12_Leetsdale-Elati Noise and EMFFiling
  • Dec 20, 2024
    Hearing Exhibit 105, Public Attachment NGK-1_Denver Metro Costs_FINALFiling
  • Dec 20, 2024
    Hearing Exhibit 105, Attachment NGK-2_Denver Metro Project ScheduleFiling
  • Dec 20, 2024
    Attachment A - Counsel HC NDAFiling
  • Dec 20, 2024
    Hearing Exhibit 105, Public Attachment NGK-4_Leetsdale-Elati CostsFiling
  • Dec 20, 2024
    Hearing Exhibit 105, Attachment NGK-5_Leetsdale-Elati ScheduleFiling
  • Dec 20, 2024
    Hearing Exhibit 106, Attachment JLC-1 - Cherokee Substation A Siting Study AreaFiling
  • Dec 20, 2024
    Hearing Exhibit 106, Attachment JLC-2 - Substation Expansion MapsFiling
  • Dec 20, 2024
    Hearing Exhibit 106, Attachment JLC-3 - Denver Metro DI Communities MapFiling
  • Dec 20, 2024
    Hearing Exhibit 102, Executable Attachment MVP-1 - PIM CalculatorFiling
  • Dec 20, 2024
    Hearing Exhibit 100, Denver Metro and Leetsdale-Elati CPCN ApplicationFiling
  • Dec 23, 2024
    Notice of Application FiledFiling
  • Dec 30, 2024
    UCA's Highly Confidetial Nondisclosure AgreementsFiling
  • Dec 30, 2024
    UCA's Nondisclosure AgreementsFiling
  • Jan 6, 2025
    The Utility Consumer Advocate’s Intervention by Right, Request for Hearing, and Entry of AppearancesFiling
  • Jan 22, 2025
    Motion to Intervene of Tri-State Generation and Transmission Association, Inc.Filing
  • Jan 22, 2025
    Attachment A - T-2022-8 9 System Impact Study Report Planning Final 5-10Filing
  • Jan 22, 2025
    Motion to Intervene and Entry of Appearance of the Colorado Independent Energy AssociationFiling
  • Jan 27, 2025
    Notice of Intervention as of Right by Trial Staff of the Commission, Entry of Appearance, Notice Pursuant to Rule 1007(a) and Rule 1401, and Request for HearingFiling
  • Jan 28, 2025
    Notice of Filing Corrected AttachmentFiling
  • Jan 28, 2025
    Hearing Exhibit 103, Attachment AWS-1, Rev. 1Filing
  • Jan 29, 2025
    24A-0560E - Subject Matter Expert HC - NDAFiling
  • Jan 29, 2025
    24A-0560E Counsel HC NDAFiling
  • Jan 29, 2025
    24A-0560E NDAFiling
  • Feb 10, 2025
    CIEA Highly Confidential Non-Disclosure AgreementsFiling
  • Feb 19, 2025
    Staff's Response to Public Service's Omnibus MotionFiling
  • Feb 19, 2025
    24A-0560E Report of Conferral and Motion to Approve Procedural ScheduleFiling
  • Feb 19, 2025
    UCA's Response to PSCo's Motion for WaiversFiling
  • Feb 19, 2025
    2025.02.19 - TS Response to Public Service's Request for Waiver of RulesFiling
  • Feb 27, 2025
    24A-0560E Motion for Leave to Reply and ReplyFiling
  • Mar 3, 2025
    Trial Staff's First Amended Notice Pursuant to Rule 1007(a)Filing
  • Mar 6, 2025
    Trial Staff's Response to Public Service's Motion for Leave to ReplyFiling
  • Mar 14, 2025
    Hearing Exhibit 107, Supplemental Direct Testimony of Michael V PascucciFiling
  • Mar 14, 2025
    Hearing Exhibit 110, Supplemental Direct Testimony of Noel G. KlinnertFiling
  • Mar 14, 2025
    Hearing Exhibit 109, Supplemental Direct Testimony of S Parker WrozekFiling
  • Mar 14, 2025
    Hearing Exhibit 108, Supplemental Direct Testimony of Gilbert Y. FloresFiling
  • Mar 14, 2025
    24A-0560E Second Motion for Extraordinary Protection_WECCFiling
  • Mar 14, 2025
    Hearing Exhibit 110, Attachment NGK-6 (Public Slip Sheet)Filing
  • Mar 14, 2025
    Attachment D - Pascucci AffidavitFiling
  • Mar 14, 2025
    Hearing Exhibit 108, Attachment GYF-1 - Power Flow AnalysisFiling
  • Mar 14, 2025
    Hearing Exhibit 108, Attachment GYF-2 - DER Comparison_3.7.25 (Executable)Filing
  • Mar 14, 2025
    Hearing Exhibit 108, Attachment GYF-2 - DER Comparison_3.7.25Filing
  • Mar 14, 2025
    Hearing Exhibit 110, Attachment NGK-7 (Public Slip Sheet)Filing
  • Mar 14, 2025
    Attachment C - Subject Matter Expert HC NDAFiling
  • Mar 14, 2025
    Attachment A - WECC Information Sharing PolicyFiling
  • Mar 14, 2025
    Attachment B - Counsel HC NDAFiling
  • Mar 14, 2025
    Non-Disclosure AgreementFiling
  • Mar 18, 2025
    UCA's WECC Highly Confidential Nondisclosure AgreementsFiling
  • Apr 7, 2025
    24A-0560E_Motion to Reschedule Technical ConferenceFiling
  • Apr 22, 2025
    Hearing Report from 04-22-2025Filing
  • May 14, 2025
    Verified Motion for Variance from Decision No. R25-0336-I, to Amend Procedural Schedule, and for Waiver of Response TimeFiling
  • May 15, 2025
    Hearing Report from 05-15-2025Filing
  • May 19, 2025
    Notice of Conferral re Variances from R25-0336-IFiling
  • May 19, 2025
    UCA's Entry of AppearanceFiling
  • May 21, 2025
    Notice of Change of Address and Telephone NumberFiling
  • Aug 8, 2025
    Hearing Exhibit 113, Second Supplemental Direct Testimony Anthony P. DeAugustinoFiling
  • Aug 8, 2025
    Hearing Exhibit 111, Second Supplemental Direct Testimony of Michael V. PascucciFiling
  • Aug 8, 2025
    Hearing Exhibit 112, Second Supplemental Direct Testimony of Jason T. StandingFiling
  • Aug 8, 2025
    Hearing Exhibit 112, Attachment JTS-1, Supplemental Analysis Report 1898Filing
  • Aug 8, 2025
    Hearing Exhibit 113, Attachment APD-2 (Public Slip Sheet)Filing
  • Aug 8, 2025
    Hearing Exhibit 113, Attachment APD-1_EnCompass Modeling ReportFiling
  • Aug 13, 2025
    Trial Staff's Second Amended Notice Pursuant to Rule 1007(a)Filing
  • Aug 15, 2025
    Public CommentsFiling
  • Aug 21, 2025
    Trial Staff's Third Amended Notice Pursuant to Rule 1007(a)Filing
  • Sep 12, 2025
    Hearing Exhibit 200, Public Answer Testimony of Staff Witness DaltonFiling
  • Sep 12, 2025
    Trial Staff's Notice of Filing Answer Testimony and AttachmentsFiling
  • Sep 12, 2025
    Hearing Exhibit 200, Attachment WJD-1, Ulteig Review of Attachment AWS-1, Rev1Filing
  • Sep 12, 2025
    Hearing Exhibit 201, Answer Testimony of Staff Witness O'NeillFiling
  • Sep 12, 2025
    Hearing Exhibit 201, Executable Attachment ETO-1, PIM ComparisonFiling
  • Sep 12, 2025
    Hearing Exhibit 201, Attachment ETO-1, PIM ComparisonFiling
  • Sep 12, 2025
    Hearing Exhibit 201, Attachment ETO-2, Response to UCA2-8Filing
  • Sep 12, 2025
    Hearing Exhibit 201, Executable Attachment ETO-3, Workpaper for Attachment NGK-2Filing
  • Sep 12, 2025
    Hearing Exhibit 201, Attachment ETO-3, Workpaper for Attachment NGK-2Filing
  • Sep 12, 2025
    Hearing Exhibit 201, Attachment ETO-4, Response to CPUC3-8Filing
  • Sep 12, 2025
    Hearing Exhibit 300, Chris Neil Answer TestimonyFiling
  • Sep 12, 2025
    Hearing Exhibit 300, Attachment CN-4_ PSCo Resp to UCA4-15Filing
  • Sep 12, 2025
    Hearing Exhibit 300, Attachment CN-5_ HE105, Siebenaler Direct_24A-0442EFiling
  • Sep 12, 2025
    Hearing Exhibit 300, Attachment CN-3_ Cowan Direct_25A-0194EFiling
  • Sep 12, 2025
    Hearing Exhibit 300, Attachment CN-2_ Denver Transmission Map 2024Filing
  • Sep 12, 2025
    Hearing Exhibit 300, Attachment CN-1_Neil CVFiling
  • Sep 12, 2025
    Hearing Exhibit 500 - Answer Testimony of Jonathan M FidrychFiling
  • Sep 12, 2025
    Hearing Exhibit 500 - Attachment JMF-8 - T-2022-8 9 System Impact Study Report Planning Final 5-10-23Filing
  • Sep 12, 2025
    Hearing Exhibit 500 - Attachment JMF-7 - Public Service Response to TSGT 1-8Filing
  • Sep 12, 2025
    Hearing Exhibit 500 - Attachment JMF-6 - ERP Phase II Stakeholder Meeting Notes 5-30-24Filing
  • Sep 12, 2025
    Hearing Exhibit 500 - Attachment JMF-5 - ERP Phase II Study 5-30-2024_FinalFiling
  • Sep 12, 2025
    Hearing Exhibit 500 - Attachment JMF-4 - PSCO ERP Phase II Study Plan 2-15-2024_FinalFiling
  • Sep 12, 2025
    Hearing Exhibit 500 - Attachment JMF-3 - ERP Phase II Stakeholder Meeting Notes 2-15-24Filing
  • Sep 12, 2025
    Hearing Exhibit 500 - Attachment JMF-1 - Jonathan Fidrych Resume 2025Filing
  • Sep 12, 2025
    Hearing Exhibit 500 - Attachment JMF-2 - ERP Phase II Study 2-15-24_FinalFiling
  • Sep 14, 2025
    Public CommentsFiling
  • Sep 15, 2025
    Hearing Exhibit 300, Chris Neil Answer Testimony, Rev 1Filing
  • Sep 15, 2025
    UCA's Notice of Revised Answer TestimonyFiling
  • Sep 15, 2025
    Hearing Exhibit 300, Attachment CN-7_Semi-Annual Report GDT & Voltage FacilitiesFiling
  • Sep 15, 2025
    Hearing Exhibit 300, Attachment CN-6_ Siebenaler Direct_24-0442EFiling
  • Sep 18, 2025
    Attorney Non-Disclosure Agreement for Highly Confidential InformationFiling
  • Oct 10, 2025
    Hearing Exhibit 114, Rebuttal Testimony and Attachments of Michael V. PascucciFiling
  • Oct 10, 2025
    Hearing Exhibit 115, Rebuttal Testimony and Attachments of Jason T. StandingFiling
  • Oct 10, 2025
    Hearing Exhibit 116, Rebuttal Testimony of S Parker WrozekFiling
  • Oct 10, 2025
    Hearing Exhibit 117, Rebuttal Testimony and Attachment Noel G. KlinnertFiling
  • Oct 10, 2025
    Hearing Exhibit 118, Rebuttal Testimony of Terri K. EatonFiling
  • Oct 10, 2025
    Hearing Exhibit 115, Attachment JTS-3_PSCO3-1_UCA Discovery ResponseFiling
  • Oct 10, 2025
    Hearing Exhibit 115, Attachment JTS-2_TSTG_Loading_ComparisonFiling
  • Oct 10, 2025
    Hearing Exhibit 114, Attachment MVP-3 - Staff Response to PSCo2-6Filing
  • Oct 10, 2025
    Hearing Exhibit 114, Attachment MVP-2 - UCA Response to PSCo2-1Filing
  • Oct 10, 2025
    Hearing Exhibit 117, Attachment NGK-8_Denver Metro ScheduleFiling
  • Oct 10, 2025
    Hearing Exhibit 115, Attachment JTS-4_PSCO3-4_UCA Discovery ResponseFiling
  • Oct 14, 2025
    Hearing Exhibit 113, Second Supplemental Direct Testimony Anthony P. DeAugustino, Rev.1Filing
  • Oct 14, 2025
    Notice of Filing CorrectionsFiling
  • Oct 14, 2025
    Hearing Exhibit 113, Attachment APD-2 (Public Slip Sheet), Rev.1Filing
  • Oct 14, 2025
    Hearing Exhibit 113, Attachment APD-1_EnCompass Modeling Report_Denver Metro CPCN, Rev.1Filing
  • Oct 14, 2025
    Attachment A, Corrections SummaryFiling
  • Oct 14, 2025
    Hearing Exhibit 102, Attachment MVP-1 - PIM Calculator (PDF)Filing
  • Oct 15, 2025
    Notice of Filing CorrectionsFiling
  • Oct 15, 2025
    Hearing Exhibit 117, Attachment NGK-8_Denver Metro Schedule, Rev.1Filing
  • Oct 15, 2025
    Hearing Exhibit 117, Attachment NGK-8_Denver Metro Schedule (Redline)Filing
  • Oct 17, 2025
    Notice of Unopposed Comprehensive Settlement in PrincipleFiling
  • Oct 20, 2025
    Hearing Exhibit 119, Comprehensive and Unopposed Settlement AgreementFiling
  • Oct 20, 2025
    Unopposed Motion to Approve Settlement and Amend Procedural Schedule and Request for Waiver of Response TimeFiling
  • Oct 23, 2025
    Hearing Exhibit 120, Settlement Testimony of Michael V. PascucciFiling
  • Oct 23, 2025
    Hearing Exhibit 120, Executable Attachment MVP-4Filing
  • Oct 23, 2025
    Hearing Exhibit 120, Attachment MVP-4Filing
  • Oct 23, 2025
    Hearing Exhibit 120, Executable Attachment MVP-5Filing
  • Oct 23, 2025
    Hearing Exhibit 120, Attachment MVP-5Filing
  • Oct 23, 2025
    Hearing Exhibit 120, Executable Attachment MVP-6Filing
  • Oct 23, 2025
    Hearing Exhibit 120, Attachment MVP-6Filing
  • Oct 23, 2025
    Hearing Exhibit 501 - Settlement Testimony of Jonathan M FidrychFiling
  • Oct 23, 2025
    Trial Staff's Notice of Filing Settlement TestimonyFiling
  • Oct 23, 2025
    HE 202, Settlement Testimony of Trial Staff William J. DaltonFiling
  • Oct 23, 2025
    Hearing Exhibit 119, Rev. 1 - Updated Settlement AgreementFiling
  • Oct 23, 2025
    Notice of Additional Settling Party and Filing of Updated Settlement AgreementFiling
  • Oct 23, 2025
    Hearing Exhibit 301, Settlement Testimony of Chris NeilFiling
  • Oct 24, 2025
    Notice of Filing Joint Cross-Examination MatrixFiling
  • Oct 24, 2025
    Joint Cross-Examination Matrix (Executable)Filing
  • Oct 24, 2025
    Joint Cross-Examination MatrixFiling
  • Dec 3, 2025
    Public CommentsFiling
  • Apr 2, 2026
    Notice of Filing of Independent Engineer Scope of WorkFiling
  • Apr 2, 2026
    Attachment A, Independent Engineer Draft Scope of WorkFiling
  • Jun 2, 2026
    Cherokee Study Preliminary Summary ReportFiling
  • Jun 22, 2026
    Attachment 12 - Monroe Substation Noise & EMF StudyFiling
  • Jun 22, 2026
    Attachment 11 - Circuits 5167-5285 Noise & EMFFiling
  • Jun 22, 2026
    Attachment 10 - Smoky Hill Noise & EMF StudyFiling
  • Jun 22, 2026
    Attachment 9 - Daniels Park Noise & EMFFiling
  • Jun 22, 2026
    Attachment 1 - Denver Metro Projects Cost Exhibit (Public Slip Sheet)Filing
  • Jun 22, 2026
    Attachment 2 - ERP Risk Register (Public Slip Sheet)Filing
  • Jun 22, 2026
    Attachment 3 - Denver Metro Projects CAR (Public Slip Sheet)Filing
  • Jun 22, 2026
    Attachment 4 - Leetsdale-Elati Projects Cost Exhibit (Public Slip Sheet)Filing
  • Jun 22, 2026
    Attachment 5 - Leetsdale - Elati Risk Register (Public Slip Sheet)Filing
  • Jun 22, 2026
    Attachment 6 - Leetsdale - Elati Projects CAR (Public Slip Sheet)Filing
  • Jun 22, 2026
    Attachment 7 - Greenwood Noise & EMF StudyFiling
  • Jun 22, 2026
    Attachment 8 - Circuit 5709 Noise & EMFFiling
  • Jun 22, 2026
    ERP & 5283 Semi-Annual Report 2026-06Filing
  • Jun 23, 2026
    Notice of Technical DifficultiesFiling
  • Aug 20, 2026
    Joint Status ReportFiling

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: Sourced from the Colorado Public Utilities Commission's public e-filing search. No structured location field is published; this project will not appear on the map until geocoded another way.