Capacity
1,280 MW
Waiting
1.0 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
West
Point of interconnection
Burns Summer Lake transmission line
Queue cluster
Transition Cluster 2
Estimated investment waiting
$1.70B
≈ 1,280,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
43.0644, -118.9872 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.