NYPA Interconnection Request 721 (Solar)

Genesee, NY

Developer: Excelsior Energy Center, LLC

Capacity
280 MW
Waiting
8.3 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
System Impact Study
Grid region
NYISO
Point of interconnection
Dysinger - N. Rochester 345kV

Estimated investment waiting

$371.6M

280,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

43.0009, -78.1928 — see the map for this project in context with others.

Timeline

  • Jan 22, 2021
    Interconnection agreement executedInterconnection agreement

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.