generation · Solar
NORTHERN STATES POWER COMPANY Interconnection Request R1036 (Solar+Other)
Sherburne, MN
Capacity
710 MW
Waiting
3.7 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
MISO
Point of interconnection
Sherburne County 345kV Substation
Expected online
Oct 2024*
* Approximate / developer-estimated date, not a firm commitment.
Estimated investment waiting
$942.2M
≈ 710,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
45.4532, -93.7692 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.