generation · Wind (onshore)
Capacity
339 MW
Waiting
9.7 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
System Impact Study
Grid region
NYISO
Point of interconnection
Stolle Rd - Five Mile Rd 345kV
Estimated investment waiting
$582.6M
≈ 339,100 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
42.2391, -78.6623 — see the map for this project in context with others.
Timeline
- Feb 8, 2021Interconnection agreement executed — Interconnection agreement
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.