WaitingForPower
generation · Gas

MidAmerican Energy Company Interconnection Request E0002 (Gas)

Adair, IA

Developer: MidAmerican Energy Company

Capacity
265 MW
Waiting
1.1 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
In Progress (unknown study)
Grid region
MISO
Point of interconnection
Northboro-Orient 345kV
Queue cluster
ERAS Study Cycle 1

Estimated investment waiting

$299.4M

265,000 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

41.3285, -94.4782 — see the map for this project in context with others.

Timeline

  • Dec 31, 2025
    Interconnection agreement executedInterconnection agreement

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.