Capacity
263 MW
Waiting
4.0 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Cluster Study
Grid region
MISO
Point of interconnection
ORIENT - NORTHBORO 345.0kV
Queue cluster
DPP-2022 West
Estimated investment waiting
$297.2M
≈ 263,000 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
41.3285, -94.4782 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.