WaitingForPower
generation · Wind (onshore)

Interconnection Request J4056 (Wind)

Marshall, IA

Capacity
310 MW
Waiting
1.0 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
MISO
Point of interconnection
Lehigh - Marshalltown (Twinkle) 345kV
Queue cluster
DPP Cycle Pending West

Estimated investment waiting

$532.6M

310,000 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

42.0417, -92.9814 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.