WaitingForPower
generation · Solar

Interconnection Request G0797 (Solar+Battery)

Wasco, OR

Capacity
650 MW
Waiting
4.1 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
In Progress (unknown study)
Grid region
West
Point of interconnection
BPA 500 KV John Day-Marion transmission line.
Queue cluster
Transition Cluster

Estimated investment waiting

$862.5M

650,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

45.1645, -121.1651 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.