Capacity
500 MW
Waiting
2.3 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
In Progress (unknown study)
Grid region
ISO-NE
Point of interconnection
The project will tap the Bourne-Jordan Pond (342) 345kV line with a new three breaker ring bus to connect the project.
Estimated investment waiting
$658.0M
≈ 500,000 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
41.7061, -70.1648 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.