generation · Wind (onshore)
Capacity
630 MW
Waiting
—
Stage
Planned, approvals not yet initiated
Verification
Verified (primary source)
Grid region
NWMT
Equipment
Wind turbine, onshore
Expected online
Oct 2031*
* Approximate / developer-estimated date, not a firm commitment.
Estimated investment waiting
$1.08B
≈ 630,000 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
46.3574, -110.3958 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No application-filed date is published by EIA-860M, so days/years waiting cannot be computed until one is added via manual override — only a planned operation date (10/2031) is available.