WaitingForPower
generation · Wind (onshore)

GREAT RIVER ENERGY Interconnection Request S1009 (Wind+Other)

Location not specified

Capacity
259 MW
Waiting
5.1 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
MISO
Point of interconnection
Pleasant Valley 161kV Substation

Estimated investment waiting

$444.8M

258,920 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address/lat-lon is published in this dataset, and this project's county couldn't be matched to a centroid (missing or unrecognized FIPS code); it will not appear on the map until geocoded another way.