WaitingForPower
generation · Gas

EKPC Interconnection Request AH1-721 (Gas)

KY

Developer: East Kentucky Power Cooperative, Inc.

Capacity
786 MW
Waiting
1.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
System Impact Study
Grid region
PJM
Point of interconnection
Laurel-Cooper 161 kV
Queue cluster
TC2

Estimated investment waiting

$888.2M

786,000 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address/lat-lon is published in this dataset, and this project's county couldn't be matched to a centroid (missing or unrecognized FIPS code); it will not appear on the map until geocoded another way.