DTE Electric Interconnection Request E0018 (Battery)

Monroe, MI

Developer: DTE Electric

Capacity
432 MW
Waiting
1.1 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
In Progress (unknown study)
Grid region
MISO
Point of interconnection
Monroe-Bayshore 315kV
Queue cluster
ERAS Study Cycle 2

Estimated investment waiting

$568.5M

432,000 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.