WaitingForPower
storage · Storage

Dominion Interconnection Request AH2-133 (Battery)

City Of Chesapeake, VA

Capacity
300 MW
Waiting
4.5 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Feasibility Study
Grid region
PJM
Point of interconnection
Fentress- Landstown 230kV

Estimated investment waiting

$394.8M

300,000 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

36.6794, -76.3018 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.