Dominion Interconnection Request AH1-716 (Battery)

James City, VA

Developer: Cardinal Energy Storage East, LLC

Capacity
650 MW
Waiting
1.4 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
System Impact Study
Grid region
PJM
Point of interconnection
Surry-Skiffes Creek 500kV
Queue cluster
TC2

Estimated investment waiting

$855.4M

650,000 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

37.3248, -76.7779 — see the map for this project in context with others.

Public Hearings