WaitingForPower
generation · Gas

Dominion Energy South Carolina Interconnection Request 20240829011 (Gas)

Colleton, SC

Developer: DESC - Generation

Capacity
338 MW
Waiting
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
Southeast
Point of interconnection
Canadys 230kV Substation
Queue cluster
D24

Estimated investment waiting

$381.4M

337,500 kW × $1,130/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

32.8494, -80.6564 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.