ConEd Interconnection Request C24-283 (Battery)
Richmond, NY
Developer: Resilient NY Storage, LLC by Hanwha Energy USA Holdings Corporation, its Manager
Capacity
349 MW
Waiting
1.9 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Grid region
NYISO
Point of interconnection
Goethals 345 kV
Queue cluster
C24
Estimated investment waiting
$459.3M
≈ 349,000 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Location
40.5613, -74.1399 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.