WaitingForPower
generation · Wind (onshore)

Chokecherry and Sierra Madre Wind (Unit I-A)

Carbon, WY

Developer: Power Company of Wyoming LLC (IPP Non-CHP)

Capacity
844 MW
Waiting
Stage
Under construction
Verification
Verified (primary source)
Grid region
CISO
Equipment
Wind turbine, onshore
Expected online
Dec 2031*

* Approximate / developer-estimated date, not a firm commitment.

Estimated investment waiting

$1.45B

844,200 kW × $1,718/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

41.6831, -107.2000 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No application-filed date is published by EIA-860M, so days/years waiting cannot be computed until one is added via manual override — only a planned operation date (12/2031) is available.