WaitingForPower
storage · Storage

Black Hills Co (CO PUC Docket 25A-0255E)

CO

Capacity
50 MW
Waiting
1.2 yrs
Stage
Local/state review
Verification
Verified (primary source)

Estimated investment waiting

$65.8M

50,000 kW × $1,316/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Timeline

  • Jun 12, 2025
    Motion of Black Hills Colorado Electric, LLC for Protective Order Affording Extraordinary ProtectionFiling
  • Jun 12, 2025
    Hearing Exhibit 101, Direct Testimony of Michael J. HarringtonFiling
  • Jun 12, 2025
    Hearing Exhibit 102, Direct Testimony of Mark L. LuxFiling
  • Jun 12, 2025
    Hearing Exhibit 100, Attachment 1 - BHCOE FinancialsFiling
  • Jun 12, 2025
    Hearing Exhibit 101, Attachment MJH-1 - PBR Revenue RequirementFiling
  • Jun 12, 2025
    Hearing Exhibit 101, Attachment MJH-2 Emissions PIMFiling
  • Jun 12, 2025
    Hearing Exhibit 101, Executable Attachment MJH-2 Emissions PIMFiling
  • Jun 12, 2025
    Hearing Exhibit 102, Attachment MLL-1 ¿ Plot PlanFiling
  • Jun 12, 2025
    Hearing Exhibit 102, Attachment MLL-2 ¿ Electrical 1-Line DiagramFiling
  • Jun 12, 2025
    Hearing Exhibit 102, Attachment MLL-3 - Build Transfer AgreementFiling
  • Jun 12, 2025
    Attachment A - Subject Matter Expert HC NDAFiling
  • Jun 12, 2025
    Attachment B - Attorney HC NDAFiling
  • Jun 12, 2025
    Attachment C - AffidavitFiling
  • Jun 12, 2025
    Hearing Exhibit 100, BHCOE Verified Application Battery StorageFiling
  • Jun 16, 2025
    Notice of Application FiledFiling
  • Jun 17, 2025
    UCA's Nondisclosure AgreementsFiling
  • Jul 3, 2025
    Notice of Intervention as a Matter of Right of the Office of the Utility Consumer AdvocateFiling
  • Jul 10, 2025
    Notice of Change of Physical AddressFiling
  • Jul 18, 2025
    Notice of Intervention as of Right by Trial Staff of the Commission, Entry of Appearance, Notice Pursuant to Rule 1007(a) and Rule 1401, and Request for HearingFiling
  • Aug 11, 2025
    Motion of Black Hills Colorado Electric, LLC for the Commission to Modify or Clarify Interim Decision No. C25-0583-I and for Shortened Response TimeFiling
  • Aug 15, 2025
    Trial Staff's Response to Black Hills' Motion to Clarify or Modify Interim Decision No. C25-0583-IFiling
  • Aug 20, 2025
    Notice of Change of Physical AddressFiling
  • Sep 11, 2025
    Unopposed Motion of Black Hills Colorado Electric, LLC to Clarify Procedural Schedule and for Waiver of Response TimeFiling
  • Oct 3, 2025
    Black Hills Colorado Electric, LLC's Unopposed Motion to Modify Procedural Schedule as a Result of Anticipated Settlement, and Request for Waiver of Response TimeFiling
  • Oct 8, 2025
    Public Attachment A - Unanimous Comprehensive Settlement Agreement_RedactedFiling
  • Oct 8, 2025
    BHCOE's Unopposed Motion for Settlement AgreementFiling
  • Oct 8, 2025
    Public Attachment 1 - PBR Revenue Requirement_SettlementFiling
  • Oct 10, 2025
    Hearing Exhibit 200, Settlement Testimony of Staff Witness O'NeillFiling
  • Oct 10, 2025
    Trial Staff's Notice of Filing Settlement Testimony and AttachmentsFiling
  • Oct 10, 2025
    Hearing Exhibit 200, Attachment ETO-1 BHCOE Responses to Discovery Request CPUC 05-01Filing
  • Oct 10, 2025
    Hearing Exhibit 200, Attachment ETO-3 Att. CPUC 5-1(a2)_Description of Revenue Requirement ChangesFiling
  • Oct 10, 2025
    Hearing Exhibit 200, Attachment ETO-4 (modified Att. CPUC 5-1(a1)_Revenue Requirement Comparison)Filing
  • Oct 10, 2025
    Hearing Exhibit 200, Attachment ETO-2 Att. CPUC 5-1(a1)_Revenue Requirement ComparisonFiling
  • Oct 10, 2025
    Hearing Exhibit 103, Settlement Testimony of Michael J. HarringtonFiling
  • Oct 10, 2025
    BHCOE Notice of Filing of Settlement TestimonyFiling
  • Oct 10, 2025
    Hearing Exhibit 103, Attachment MJH-1 - Unanimous Comprehensive Settlement AgreementFiling
  • Oct 10, 2025
    Hearing Exhibit 300, Attachment LHS-1_Henry CVFiling
  • Oct 13, 2025
    Hearing Exhibit 300, Settlement Testimony of Henry Sermos, Rev. 1_PublicFiling
  • Oct 13, 2025
    UCA Notice of Revised Settlement TestimonyFiling
  • Oct 13, 2025
    UCA's Highly Confidential Nondisclosure AgreementsFiling

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: Sourced from the Colorado Public Utilities Commission's public e-filing search. Capacity figure is parsed from the docket title text, not a structured field — not independently verified. No structured location field is published; this project will not appear on the map until geocoded another way.