Capacity
201 MW
Waiting
—
Stage
Completed
Verification
Verified (primary source)
Estimated investment waiting
$266.9M
≈ 201,100 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.
Timeline
- Jun 8, 2022Notice of Participation — Completed
- Jun 22, 2022Pre-filed Testimony — No Action
- Jun 29, 2022Pre-filed Testimony — Completed
- Jul 11, 2022Rebuttal Testimony — Completed
- Jul 21, 2022Comments — Completed
- Aug 1, 2022Hearing — No Action
- Aug 2, 2022Hearing Continued — Completed
- Aug 29, 2022Comments — Completed
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: Sourced from the Virginia State Corporation Commission's public docket search — an "unofficial" copy per the SCC's own disclaimer, provided for public convenience. Capacity figure is parsed from the case caption's prose, not a structured field — not independently verified. No structured location field is published for this docket; this project will not appear on the map until geocoded another way.