Capacity
500 MW
Waiting
2.3 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Cluster Study
Grid region
West
Point of interconnection
Hassayampa- North Gila 500kV
Estimated investment waiting
Not estimated: No published typical capital cost is used for fuel type "other" in v1, so no dollar estimate is shown for it.
Location
33.3452, -112.4989 — see the map for this project in context with others.
Public Hearings
Unknown
Hearing details: Unknown
Not available from this project’s data source yet. Check the sources below directly.
Sources
Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.