WaitingForPower
generation · Solar

Arizona Public Service Interconnection Request Q402 (Solar+Battery)

Navajo, AZ

Capacity
750 MW
Waiting
4.9 yrs
Stage
Interconnection study
Verification
Verified (primary source)
Queue stage
Cluster Study
Grid region
West
Point of interconnection
Cholla 500kV

Estimated investment waiting

$995.3M

750,000 kW × $1,327/kW typical overnight construction cost (EIA) — the dollar value of the power plant itself sitting in permitting limbo, not a bill estimate. Full methodology.

Location

35.3908, -110.3210 — see the map for this project in context with others.

Public Hearings

Unknown

Hearing details: Unknown

Not available from this project’s data source yet. Check the sources below directly.

Sources

Data quality note: No exact site address is published in this dataset — the map pin is placed at the project's county centroid, not its actual site.